18th & Kellogg Reservoir Replacement (P1810-19)

Project Description

This Capital Improvement Project involves; a new access road to the site, relocation of two transmission mains across the site, construction of a new 6 million gallon concrete reservoir, installation of a new 30-inch inlet/outlet pipeline, construction of a new pumping station, an onsite overflow detention basin, demolition of both existing reservoirs and finally re-landscaping of areas impacted on the park site.P1810 Site Plan

Important Dates

Start Date:March 23, 2020
Estimated End Date:
July 13, 2022
Funding Source:
Utility bonds
Estimated Cost:
$15,079,560.00

Project Contacts

P1810 Updated Contacts

Status

Contractor has successfully installed both offsite discharge pipelines and fully excavated the new reservoir location. The contractor will be working on constructing the new reservoir during the next year (fall 2020 thru end of 2021). A new reservoir inlet/outlet pipeline will be installed across the adjacent park during the winter of 2020/2021 (weather permitting). Construction of a new pumping station will be performed during the summer of 2021. De-construction of the existing concrete reservoir will occur near the end of this project in early 2022.

Click here to view the site plan and a perspective sheet!

Last updated 10/26/2020